Finland has ordered work to pause at two planned Google data centre sites after regulators raised concerns that major land-clearing and construction activity took place before mandatory environmental impact assessments were completed.
The decision affects projects in Muhos and Kajaani and could delay Google’s planned expansion of artificial-intelligence infrastructure in Finland. The case highlights the environmental and legal scrutiny facing data centres as demand for AI computing capacity grows across Europe.
What Finland has ordered
The Finnish Supervisory Agency, known as LVV, has instructed Tuike Finland, the company representing Google in the projects, to immediately suspend preparatory measures that could significantly alter the environment at the two sites.
The agency said the halt must be in place no later than 23 October 2026. Tuike Finland has also been asked to provide an explanation and outline how it plans to proceed by 14 October.
If the company does not comply, LVV said it may begin enforcement proceedings. The regulator’s investigation concerns whether hundreds of hectares of forest were cleared without the environmental impact assessment required under Finnish law.
Work already carried out
According to Tommi Muilu, head of LVV’s environment department, activity at the sites has included:
- Tree removal and forest clearance
- Stripping of topsoil
- Construction of site roads and storage areas
- Changes to drainage ditches
The Finnish Association for Nature Conservation said more than 300 hectares had been deforested in areas that it considered important for protection. That assessment was attributed to the organisation and remains part of the wider dispute over the sites’ environmental impact.
Google acknowledges environmental shortcomings
Google spokesman Sondre Ronander said the company understood the concerns and had not met its own environmental standards in the case. He said Google would review LVV’s findings and follow the agency’s guidance.
Ronander also said the company had acted in good faith and had carried out environmental surveys and mitigation measures. Google is advancing landscaping and biodiversity plans, including tree planting across 130 hectares at the Muhos site.
Those commitments do not remove the regulatory issue. The immediate question is whether the preparatory works complied with Finnish environmental assessment requirements and whether further construction can proceed lawfully.
Why the projects matter to Google
Google announced in September that it planned to invest €13 billion in Finnish digital infrastructure over the following two years. The company described the investment as its largest single investment in Europe.
The facilities are intended to support Google’s artificial-intelligence ambitions and broader cloud-computing operations. Data centres require substantial land, electricity, cooling infrastructure and network connections, making their development an increasingly important issue in European technology and energy policy.
The Finnish case illustrates the tension between rapid investment in AI infrastructure and national rules designed to protect forests, soil, water systems and biodiversity. Even when a project has major economic or technological significance, developers must comply with the applicable planning and environmental procedures.
Projects likely to face delays
Finland’s Minister of the Environment and Climate, Sari Multala, said the projects would likely be delayed because of the problems surrounding the environmental assessments.
Multala said companies operating in Finland must comply with Finnish law. Her comments underline that the matter is a national regulatory decision rather than a new European Union rule or a decision by an EU institution.
The regulator’s order does not, based on the information available, cancel Google’s investment plans or permanently block the data centres. It pauses specified preparatory activity while the environmental and legal questions are examined.
What happens next?
The next steps will depend on Tuike Finland’s response and the findings of the Finnish Supervisory Agency. The company must explain its position and describe how it intends to proceed. The agency can then determine whether additional enforcement action is necessary.
Key issues include:
- Whether the environmental impact assessments were legally required before the reported works began
- Whether further preparatory activity can resume
- What remedial or biodiversity measures may be required
- How the regulatory process affects the timetable for construction
The episode may also influence how future large-scale data centre developments are planned in Finland and elsewhere in Europe.
Broader implications for Europe’s AI infrastructure
Europe is seeking more computing capacity for artificial intelligence, cloud services and digital platforms. At the same time, communities and environmental authorities are examining the land, water and energy consequences of large facilities.
Data centre proposals can bring investment, jobs and digital infrastructure, but they can also involve forest clearance, new roads, changes to drainage and significant electricity demand. Environmental assessments are intended to identify those effects before irreversible work takes place.
The Finnish dispute therefore has relevance beyond the two sites. It shows that AI expansion is subject to national planning and environmental law, even when projects are presented as strategically important investments.
Conclusion
Finland’s order places a temporary halt on preparatory work at Google’s planned data centre sites in Muhos and Kajaani while regulators assess whether environmental requirements were followed. Google has acknowledged shortcomings and said it will study the findings, while Finnish authorities have warned that the projects may be delayed.
The case is an important reminder that Europe’s AI infrastructure drive must proceed alongside environmental compliance. For Google, the immediate priority is to respond to the Finnish regulator and establish how the projects can move forward within the law.